Verify the finished graded surface
Verify the finish by comparing measured levels with the agreed target at recorded points. A smooth-looking surface can still have local lows or an interrupted water route.
Illustrative 200 mm fall over 100 m
| Distance | Example target level | Field check |
|---|---|---|
| 0 m | 10.000 m | Record actual level and difference from target. |
| 25 m | 9.950 m | Check cross-section and local low points. |
| 50 m | 9.900 m | Check transition between passes. |
| 75 m | 9.850 m | Check the continuity of the water route. |
| 100 m | 9.800 m | Check connection to the outlet. |
The target levels above are illustrative values referenced to an arbitrary datum. Agree measurement spacing and acceptance tolerances for the actual project. Check the grade instrument against a known reference before relying on the results.
Keep a handover record
- Target surface, benchmark, instrument and check date.
- Measured levels and deviations at the agreed locations.
- Any soft material, settlement or outstanding work.
- Who checked and accepted the finished surface.