Check fall and drainage before grading
Calculate the target fall from distance and slope, then verify that the outlet and downstream water level allow the intended route. Record all levels against one benchmark.
Worked grade example
For an illustrative 100 m run at 1:500, fall = 100 ÷ 500 = 0.20 m = 200 mm. This is a 0.2% slope. The 200 mm is the intended change across the full run; individual humps and hollows must still be surveyed.
Fall (m) = horizontal distance (m) ÷ grade denominator
Percent slope = 100 ÷ grade denominator
Percent slope = 100 ÷ grade denominator
A target plane and the existing ground are different surfaces. Use their level differences to calculate the cut-and-fill plan. Include the receiving outlet before moving soil.
What to bring to a design discussion
- Boundary and surface survey, benchmark and measurement method.
- Purpose of the surface, allowable water depth or required drainage route.
- Inlet, outlet, downstream constraints and level records.
- Topsoil, material, access, tractor and the finish required by the project.
Verify the finished surface against the same benchmark.